Last August, Stolt Offshore completed
the largest subsea welded hot
tap to date in the UK sector of the
North Sea, following a carefully planned series of operational trials. Stolt
designed the 18-in. hot tap to facilitate oil export from the Nexen-operated
Buzzard field, currently under development, into the 36-in. BP owned and
operated Forties Pipeline System (FPS). The latter is a major energy
artery transporting 600,000 b/d, equating to output from over 30 fields in the
central North Sea.
From the outset of the project, BP
insisted there was to be an extensive assurance process for each stage of the
project, and there could be no interruption to existing FPS activities during
the tie-in operation.
Stolt used its experience from four
previous welded subsea hot
taps in the North Sea and proposed a
series of trials and practice runs to demonstrate to all stake holders that the
offshore operations would run according to plan.
There were some challenges specific to
this project. First, all the previous hot tap assignments had
applied to gas export facilities - Buzzard's would be the first oil
export hot tap. second, due to the requirement for pigging, Stolt
would have to take care in obtaining the tight tolerances needed to minimize
the lip between the cut hole in the parent pipe and the inside of the branch
nipple.
In preparation, Stolt implemented a
meticulously planned program of familiarization and training for personnel
connected with the two key stages of the project, i.e., the hyperbaric welding
phase and the hot tap phase.
Hyperbaric welding
To meet its commitment concerning
non-interruption of FPS flow during hot tap construction,
Stolt applied its patented induction heating system in two of the four welds,
namely the buttering layer onto the FPS and the branch nipple to FPS butt weld.
Another prime objective was for Stolt to
achieve good hyperbaric welds in a safe manner and in an optimum time-frame.
Key to achieving this goal was the selection of a competent and experienced
welding dive team that would work effectively and coherently as a team, who
were fully acquainted with all the equipment and processes, and who would
participate in appropriate 'dry runs' or trials to achieve the sought-after
state of readiness.
Stolt assembled the welding dive team at
the National Hyperbaric Centre (NHC) in Aberdeen 14 weeks prior to mobilization
to run through the stages of preparation.
In the latter stages, additional
non-destructive testing (NDT) divers were brought in, ensuring that the
offshore dive team had full understanding of all the tasks to be performed
offshore.
The welding team produced special weld
simulators to represent the full flow conditions of oil through the FPS. The
team employed these during the welding qualifications and the full-scale
onshore welding trials. It then added cooling elements internally, fabricated
from spare joints of the FPS, to recreate the heat dissipation effect of the
oil flowing through the FPS.
The culmination of the familiarization
and qualification program was a full-scale onshore welding trial performed
within the welding habitat, using a weld simulator and the induction heating
system. The weld simulator represented the FPS and the associated cooling
effect of hydrocarbon flow within the pipeline.
The welding team employed the induction heating system for the buttering and
branch to main pipeline weld. The team performed all four welds and
subjected them to full NDT examination, then installed and fully fitted the
reinforcement sleeve.
All operations conducted within the
riggedup habitat mimicked exactly the intended offshore operations. This
included communications with the welder divers and equipment storage and
deployment within the habitat The operation took 24 hours, with standard diver
rotations.
In a hyperbarically welded hot tap operation, all preparatory activities, such as
welding, should not impact the integrity of the parent pipeline. The specific aim of the hot tap is to break this integrity in a meticulously
engineered and controlled manner.
Early in the project, Stolt awarded TD.
Williamson the contract to supply the hot tap equipment. Two
complete systems were required to ensure 100% redundancy on all items. A subsea
hydraulic power unit, controlled via an electrical umbilical and a topside
electrical control cabinet on surface, powered the tapping machine, which was
itself pressure balanced. This allowed the tapping machine body pressure to
equalize with the pipelinepressure when containment was broken. This facility
ensured that the components within the tapping machine were only exposed to
cutting loads with no additional pressure loading generated by the pipeline pressure.
As part of the assurance process, both
tapping machines were subjected to a 24-hour strength test. Analysis of the
main components and seals materials confirmed that the tapping machine could remain
attached to thepipeline while exposed internally to hydrocarbon for up
to six months without any possible loss of containment.
Three separate cutting trials were
staged to:
- Examine the operability of the tapping equipment
- Determine the optimum machine settings for cutting into Forties pipeline material
- Examine the durability of the pilot drill and cutter assemblies
- Investigate the swarf size and location of swarf deposits during the tapping process.
In parallel, divers and dive supervisors
who would be operating the hot
tap machine offshore completed a
comprehensive diver training program. This allowed the dive teams to
familiarize themselves with the equipment that would be used subsea and to
operate it in advance of the actual operation.
Diver training focused on:
- Set-up of the tapping machine and connecting the hydraulic control system
- Operation of the tapping machine and familiarization with the devices used for monitoring the progress of thetap
- Performance of contingency procedures to address plausible events that could occur during the tapping process, such as difficulty in removing the hot tap machine from the branch assembly.
The team made 20 cuts through
30-mm-thick X65 grade flat plate steel. Flat plate would provide the most onerous
cutting environment for the tapping machine, as all the cutter teeth would be
engaged on the cutting surface simultaneously. This trial run demonstrated the
tapping machine's durability. It also allowed the team to examine the
effectiveness of the integrated pipe coupon retention system.
A jig simulated the distance the cutter
would travel when moving from its storage position to engagement on the crown
of the pipeline. Where relevant, the geometry of the jig was an exact
duplication of the complete welded branch assembly. During each tap,
the process was monitored for stalling of the tapping machine, bluing of the
steel swarf, and unexpected hydraulic pressure increases within the drive unit.
This program allowed the team to establish the optimum settings for the hot tap machine.
Cutting trials on spare pipeline sections
The main aims of the second set of
trials were to facilitate practice, to demonstrate the effectiveness of the
cutter centralizing mechanism, and to prove that the selected cutter would cut
through actual sections of the FPS 36-in. pipeline.
On completion of previous hot taps, the residual internal lip left within the branch
nipples had been about 20 mm (on radius), because there was no requirement to
pig the hot tap assemblies. As the branch line from Buzzard will
export oil into the EPS, however, this particular hot tap had to be piggable, necessitating reduction of
the internal lip size to 6 mm (on radius). To this end, the team employed a
410-mm cutter inside the 422-mm ID branch nipple. Due to the tight tolerances,
the team fitted a centralizing device to the back of the cutter to ensure that
the removed coupon was concentric with the internal diameter of the branch
nipple.
It constructed a second jig for these
trials to accommodate the spare sections of Forties pipe. As previously, the
dimensions of the set-up replicated that of the subsea hot tap arrangement.
A comprehensive series of cuts
demonstrated the durability of the hot tap machine, the
successful removal and retention of each trial cut coupon, and the
functionality of the centralization mechanism. Following closer examination of
the internal lip profile, the centralizing mechanism functioned as expected.
The produced lip was of the required size and was concentric to the inner
diameter of the branch nipple.
To ensure diver safety and to minimize
potential contamination of the marine environment, the team purged the void
between the hot tap machine and upper gate valve seal of hydrocarbon
before disconnecting the hot
tap machine from the gate valve.
Purging trials then examined the effectiveness of the proposed cleansing agents
and also determined the flushing volumes needed to achieve an acceptable level
of hydrocarbon content within the void space.
The team performed a final dry run trial
prior to mobilization of the offshore operations. The objectives were to
facilitate a final practice on the hot tap, rehearse
construction activities, and demonstrate preparedness. This trial consisted of
a complete dry run of all the construction activities that were to be performed
in the forthcoming offshore phases of work - with the exception of the
hyperbaric welding operations that had previously been subjected to a separate
dry run rehearsal.
The team deployed a previously prepared
welded hot tap assembly, replicating the expected configuration
of the hot tap branch nipple and reinforcement sleeve
arrangement, welded onto a spare section of Fortiespipeline. The team fitted the line pipe section with flanges
at either end to allow the pipe section to be pressurized to the line pressure
anticipated at the offshore worksite, using diesel as the pressurization
medium.
It positioned the simulated assembly
within the confines of the hot
tap protection structure with
the hot tapbranch nipple positioned relative to the protection
structure as expected offshore.
Once the team established this
arrangement, it performed a further series of trials:
- The upper structure mated with the lower structure to ensure they could mate correctly
- The pile locking mechanism was tested using test sections of the fabricated piles
- The hot tap pipe work support clamps were installed onto a test section of 36-in. pipe and secured
- All temporary works items which interfaced with the main structure, were test fitted to verify correct fitting and operation.
Finally, the team performed a full hot tap in the pressurized simulator. It set the tapping
machine operational parameters in accordance with the criteria established in
the hot tap trial program. To simulate the communication
lines offshore, trained divers operated the hot tap machine under
direct instruction from the dive supervisor via a UHF radio link.
Last July and August, Stolt performed the offshore construction activities from the Seaway Eagle and Seaway Osprey DSVs. The program proved to be 100% successful, with a smooth execution of the cutting operation resulting in the removal and recovery of the pipe coupon.
Sumber : McCann, Joe; Kirk, Matthew. "Welding Preparations Pay Off for Forties Pipeline Hot Tap". 27 Januari 2014. http://search.proquest.com/docview/227331145?accountid=31562


Tidak ada komentar:
Posting Komentar