Minggu, 02 Februari 2014

Pipeline corrosion Risk Analysis - An Assessment of Deterministic and Probabilistic Methods

Pipeline Integrity Management is the management of pipeline assets such that availability is maximised at optimum cost, without compromising environmental, safety and legislative standards. This is achieved when, under specified operating conditions, risks of failure endangering the safety of personnel, environment or asset value are as low as reasonably practicable.
Oil and gas pipelines can become susceptible to a whole variety of threats throughout operational life, which if not adequately mitigated against, may eventually compromise pipeline integrity. One of the primary life-limiting threats is internal corrosion and therefore the requirement for effective corrosion management is vital. In essence, a corrosion management strategy should be risk-based and should take account of all aspects of asset maintenance, corrosion rate activity, historical and future operational parameters and the management and business requirements.
Risk-based pipeline corrosion management strategies, developed subsequent to the performance of a corrosion risk assessment, deliver benefits in that pipeline inspections and corrosion control/mitigation activities may be targeted specifically at those pipeline assets that are assessed as high risk (i.e. high probability of failure and high consequence). Corrosion management is essentially a "closed loop" (iterative) process where the corrosion risk assessment is central to the management process. The purpose of this paper therefore, is essentially a critique of the methods commonly used to assess pipeline corrosion risks.
Risk assessment
Risk is defined as the combination of the probability of the occurrence of an event and the magnitude of the consequences of the occurrence (The Engineering Council, 1993). Risk analysis is a structured process that identifies both the likelihood and extent of adverse consequences arising from a single given activity. A Risk Assessment is the integrated analysis of risks inherent to a pipeline and their significance in an appropriate context. Therefore, a "Corrosion Risk" is the probability of corrosion failure and the consequences, in terms ofhazard to personnel and asset availability, which would result should a loss of containment occur.
There are essentially two ways of assessing pipeline corrosion risks: deterministically, where this can be approached cither qualitatively and/or semi-quantitatively, and probabilistically, where quantitative risk assessment methods arc employed.
The traditional deterministic approach to the assessment of pipeline corrosion risks is typically based on the judgement of "competent engineering personnel" as the paradigm for identifying risk. Semi-quantitative (deterministic) methods essentially substitute the analytic of science for the fallible judgement of "competent personnel", with the explicit notion that scientific treatment provides a superior basis for reliable prediction; an opinion which must surely be true. Probabilistic approaches deal with uncertainties in the input data by employing probability density distributions. Implicit in the assessment approach is the claim that rigorous application of probability theory will yield a superior conceptual framework for understanding and managingrisk; this notion is clearly untrue, however this does not mean that probabilistic treatments should never be used in the management of risk. It is clearly the case that the way the various risk assessment techniques are applied is a matter of more subtlety than is often thought.
During this work the comparison of deterministic and probabilistic methods was made using the same basic inputs, where the former approach made use of mean values and the latter probability density functions. For probabilistic assessments, statistical analyses of the input data were performed in order to discern the form of each probability density function. However, limited knowledge of certain of the primary input variables did preclude statistical analysis. In these, instances a normal distribution of values was assumed (e.g. the natural spread of pipeline nominal wall thickness was assumed to be normally distributed, where the limits of the distribution were based on the API specification (American Petroleum Institute, 2000)).
Fourteen in. main oil export pipeline
The pipeline chosen for this review is a 16.1 km long, 14 in. main oil export line in the North Sea. It is a submarine pipeline constructed in API 5L X60, with a nominal wall thickness of 14.3 mm (0.559 in.), and was just over three years into its period of operation, with a design life of 25 years. The service conditions are relatively warm with typical crude oil inlet temperatures of the order of 65°C and outlet temperatures of approximately 30°C; the pipeline bathymetry and thermal profile are shown in Figure 1. The pipeline is currently operated at a pressure of 20 bara where the maximum allowable operating pressure (MAOP) is 140 bara.
Various initial screening assessments were performed in order to determine the susceptibility of the pipelineto a variety of internal corrosion threats which included microbial corrosion, sulphide stress corrosion cracking, CO^sub 2^ corrosion and fluid and solids erosion. In particular, the initial screening assessments had shown that the crude oil velocity (approximately 0.4m/s (1.3ft/s)) was too low to prevent water drop out in thepipeline even when present in small quantities. Calculations had yielded a critical crude oil velocity in the region of 1.1 m/s (3.6ft/s) for the avoidance of water drop out in the line; this indicates that the internal surface of the pipeline would likely experience water-wetting during normal operation. The initial screeningassessments had shown that the primary corrosion threat to the pipeline was internal CO^sub 2^ corrosion, where all other potential failure threats were deemed to be negligible.

The pipeline is dosed continually with a corrosion inhibitor in order to mitigate against any corrosion that could occur where water accumulations develop in the line. Indications from both laboratory-based and field-based trials were that inhibition in the region of 85-90 per cent was achievable. The corrosion risk assessments therefore were performed with CO^sub 2^ corrosion as the dominant threat and that inhibition at 85-90 per cent was achievable. Corrosion rates were predicted during this work using the model of (deWaard and Lotz, 1993), the current CO^sub 2^ concentration (2.25 mole per cent) and calculated thermal profile data.
The consequences of failure for this pipeline, a main oil export line, were assessed as "High" and therefore when considered in the context of risk, it is clear that the probability of failure for this pipeline was the primary driver. For pipelines which are used to transport liquid and/or gaseous hydrocarbons, the consequences of failure arc likely to remain unchanged ("High") and therefore when managing "risk" this invariably means managing pipeline failure probabilities.
Deterministic approach

The above approach therefore based the probability of failure on a predicted time to failure - the pipeline remaining life. In the present case, the remaining life values (R(z)) were used as the basis for determining whether pipeline failure probabilities were either "High", "Medium" or "Low". The threshold values of R(z) together with the correspondingpipeline failure probabilities are as shown in Table I.
Probabilistic methods

Probabilistic assessment methods are considerably more labour-intensive than are deterministic methods, therefore given the level of effort required it was not feasible to assess the entire length of the pipeline using probabilistic analysis. It was decided that, based on the pipeline bathymetry and thermal profile data (Figure 1),assessments would be performed at two specific locations along the pipeline: in the region of kilometre point KP0 to KP0. 1 (i.e. the first 100m of the sealine), and within KP5 to KP6. Both locations were "low" points in the line where temperatures were warmer and the propensity for water "pooling" was deemed to be high. The approach made use of probability density functions of the basic input variables as opposed to mean values as used in the deterministic approach.
Service limit assessment

The first probabilistic method used, that of the "Service Limit"assessment, was essentially an assessment of pipelineremaining life performed probabilistically. The analysis involved estimating the respective distributions of cumulative corrosion damage at various specified future time intervals and comparing each with regard to the corrosion allowance; the approach used is shown in Figure 2.
Reliability analysis methods

Quantitative failure probabilities were determined in this paper using the first order reliability method (FORM). The methodology involved in the application of this technique is presented in considerable detail elsewhere (Cizeli et al., 1994; WS Atkins Science & Technology for HSE, 1997; WS Atkins Science & Technology for HSE, 1999; BOMEL Ltd for HSE, 2001; WS Atkins Consultants Ltd for HSE, 2001) and therefore only a brief synopsis is presented in the following.

In the case of Monte Carlo simulation, there is an obvious relationship between the number of trials N and the degree of accuracy on P^sub f^. By performing a large number of iterations, the ratio of the number of failure outcomes to the total number of iterations tends to the exact probability of failure. The primary limitation is the number of iterations required, and although Monte Carlo simulations are easily applied, they are more or less limited to determining failure probabilities in the vicinity of 10^sup -5^ per year and above (10^sup -5^ per year failure probability would require approximately 10^sup 7^ iterations to be performed).
Monte Carlo simulations were used during this work as the primary yard-stick upon which to determine the accuracy and validity of FORM. Monte Carlo simulations make no assumptions about the nature of the limit state equation, unlike FORM where this is assumed to be linear; inaccuracies resulting from FORM are often manifested as a direct consequence of the non-linear variation of all points along G(x) = 0; in such cases, the more detailed second-order reliability method (SORM) is often required. Indeed, statistical errors may also result in FORM or SORM when transforming the basic variables to equivalent standard normal variables. Transformation of variables and the assumptions in respect of the nature of the limit state equation are avoided in the Monte Carlo simulation; these numerical simulations therefore, were used during this work to validate the results obtained using FORM.
Results - deterministic assessment
Deterministic analysis had yielded a corrosion rate profile for the entire 16.1 km length of the sealine. The corrosion rate algorithm yielded a base corrosion rate which was then modified for inhibition at 85 per cent and 90 per cent - the profiles for which are as shown in Figure 5.
Pipeline remaining life was determined using the present operational envelope as the basis for the assessment; the calculation is as illustrated above in equation (1). This yielded a remaining life profile for the entire length of the pipeline which varied from approximately 12-18 years at the pipeline inlet and approximately 47-70 years at the outlet; the spread of remaining life values at each point along the pipelinereflected the perceived corrosion inhibitor effectiveness.
In terms of determining a likely probability of failure, the approach is as detailed below in Table I and this yielded a worst-case failure probability of "Medium". A corrosion management strategy would then be developed on the basis of a "Medium" probability of failure and a "High" consequence, but this approach is clearly a subjective classification of risk.
Results - probabilistic assessments
The results from the "Service Limit" assessment are shown in Figure 6 where the illustration shows the variation of the probability of exceeding the corrosion allowance in the vicinity of the first 100m of the sealine with time. The variation of probability with time indicates that in approximately 8 years from the time of thisassessment the probability of exceeding the corrosion allowance starts to become significant; with a probability of approximately 10^sup -2^. These data mean that that the pipeline would still be operable even when relatively high probabilities are encountered, but significantly its integrity will become increasingly impaired. Unfortunately, however, it is merely an indicator that pipeline failure may occur at some point when the corrosion allowance is exceeded.


Using the Service Limit assessment data clearly requires care; a target probability can be chosen, and a strategy for corrosion management developed on the basis of the time to reach this target. However, choosing an appropriate level is difficult as it cannot be guaranteed that the pipeline would not be excessively at risk when at or near the chosen value. The probability of exceeding the corrosion allowance is not a failure probability and this is its primary weakness.
The variability in pipeline failure probability with time, predicted using both the FORM and Monte Carlo simulation methods is shown in Figure 7, and as can be observed the failure probability increases over the time periods considered, consistent with an increased level of corrosion damage with time. Notably, the agreement between failure probabilities predicted by both FORM and Monte Carlo simulation (within the more limited range of the latter) was exceptionally good, suggesting that predictions from either method were reliable. As before, the spread of predicted failure probabilities reflects the perceived corrosion inhibitor effectiveness.
Using probabilistic output data for corrosion management purposes is generally a matter of choosing an acceptable maximum failure probability and developing a strategy to ensure that it is not over-stepped. In this exercise the DNV criteria (Submarine Pipeline Systems, 2003) were considered appropriate, where failure probabilities of 10^sup -5^ and 10^sup -4^ for "High" consequence and "Normal" consequencepipeline segments, respectively, were used as the basis for determining the schedules for the performance of thorough inspections (where the integrity status of the pipeline would be formally established through inspection). Indications were that within the first 100m of the sealine (which was considered a high consequence section) the time to reach the target failure probability (i.e. 10^sup -5^ per year) was of the order of 8.5 to 13 years, where the variation as indicated was dependent upon the effectiveness of corrosion inhibition; for KP5-KP6 (which was considered as a normal consequence section) this was of the order of 15.5 to 23 years (again, the variation as indicated was dependent the effectiveness of corrosion inhibition). Clearly the strategy for managing pipeline corrosion would be expected to be driven by the most susceptible section of the pipeline; although notably, quantitative estimates of failure probability were determined based on the natural variability of the basic input parameters, where this had not been possible using the deterministic approach.
Summary comparison

Comparing the output results from the two assessmentapproaches was particularly interesting. The deterministicassessment had yielded a worst-case failure probability of "Medium" with a corresponding consequence of "High"; classifications which are clearly subjective. The "Medium" failure probability classification in reality actually covers a relatively large window of remaining life (in this case 5-15 years) and therefore actions based purely on a "Medium" failure probability and "High" consequence (to reflect risk), may mean being overly conservative if the pipeline is at the top-end of the remaining life window, and the converse for those pipelines located at the lower end. Therefore in addition to the assessed failure probability, consideration should also necessarily be given to remaining life when developing a strategy based on deterministic assessments of risk for managing corrosion. Generally, a reasonable approach would be to make use of the half-life rule in particular for scheduling pipeline inspections; indications from this work would suggest that scheduling within the next 6 to 9 years would appear appropriate, although this depends on how effective corrosion mitigation activities are in practice.

The probabilistic assessments had quantified pipeline failure probabilities, though it is important to note that more effort was required when performing such an assessment. Using target probabilities for "High" and "Normal" consequence pipelinesegments (Submarine Pipeline Systems, 2003), indications were that between 8.5 and 13 years was the time period for which the target (predicted) failure probabilities would be reached, again depending on how effective corrosion mitigation activities are in practice. Basing pipeline inspections in particular on the outputs from the deterministic assessment would therefore be conservative in this instance; but this may not necessarily always be so. That the probabilisticassessment indicates that inspections justifiably may be extended beyond that suggested by the deterministicassessment is a clear benefit, in that it affords the opportunity to defer expenditure on pipeline inspections to a later date, but it may be the case that the converse may be required. It may be argued therefore, that probabilistic assessment provides a superior basis for driving pipeline corrosion management activities given that the approach deals with the uncertainties in the basic input data.
Conclusions
The deterministic approach has the distinct advantage of simplicity and the capability of being applied to an entire pipeline or collection of pipelines relatively easily. The deterministic approach therefore lends itself to ease of the application. The disadvantages of the deterministic approach may often, but not entirely be linked to inaccuracies in the input data, but notably it is the inability to deal with uncertainties in the input data that is the primary weakness. This may lead to an underestimation of the likelihood of failure or overestimating the true "risk" associated with current pipeline operations. In other words, the outputs from deterministicassessments can be rather uncertain. In certain circumstances more conservative approaches may be employed which make use of more extreme values of the basic input variables and this may make the outputassessments of risk overly conservative.
The primary advantage of probabilistic assessment is that it facilitates quantification of failure probability on the basis of uncertain data. The probabilistic approach overcomes the seemingly arbitrariness of selecting contingencies in the deterministic method and causes attention to be focused on the degree of "risk" associated with pipeline operations. The probabilistic approach reduces the weakness in the deterministic method concerning the assumptions made with regard to the input variables, but this does not necessarily remove the possibility that important parameters are omitted, or perhaps even misjudged. Nevertheless, the use of probabilistic methods should allow better management decisions to be made based on evaluation of the primary threats to a given pipeline. There are disadvantages in that it is intensi

ve, time consuming and can be very complex. In addition, the inherent strength of probabilistic methods is often compromised in two areas which can limit application. The first of these is the data available to support the calculation of "risks" and the calculation methods themselves. When performing a probabilistic assessment certain assumptions regarding the input data may have to be made; using engineering judgement often provides reasonable results, which can be improved upon in the future. In certain instances however, the lack of available data may actually preclude the use of probabilistic assessments. This problem is generally masked in the deterministic approach by the broad assumptions of what constitutes a credible threat. The second area is the choice of the target level of "risk", which in its simplest form in this case was based on predefined target levels for "High" consequence and "Normal" consequence pipeline segments (Submarine Pipeline Systems, 2003). Clearly, a choice has to be made as to what constitutes an "acceptable level of risk" and a strategy of risk management developed to ensure that this target level is not over-stepped. Nevertheless, in view of such limitations, it may be concluded that a probabilistic assessment approach which effectively mirrors pipeline operations, provides a superior basis upon which to manage risk and would therefore likely maximize both safety and business performance.

Sumber : Lawson, K. "Pipeline corrosion Risk Analysis - An Assessment of Deterministic and Probabilistic Methods". 27 Januari 2014. http://search.proquest.com/docview/218907935?accountid=31562

Tidak ada komentar:

Posting Komentar