Buried and submerged pipelines are protected from external corrosion by a coating system, which is
considered passive. Coatings are practically always applied to pipe lengths
in specialized coating plants, and continuity of coverage is ensured
after girth welding through field joint coatings (FJC).
Cathodic protection (CP) is an essential, complementary, "active"
protection system aimed at preventing corrosion at coating defects, where the pipe steel surface is exposed
to the corrosive electrolytic environment. As long as coatings remain bonded to steel and CP is correctly
applied, monitored, and maintained, no corrosion risk
exists.
The majority of known corrosion cases result from disbonding of coatings, which may prevent access of the cathodic protection
current to steel. The cause of failure, known as the "CP current shielding
effect," appears to be a concern limited to buried pipelines onshore. Cases of corrosion and stress corrosion cracking
(SCC) on old buried pipelines coated "on the ditch" with coal tar or
asphalt enamels or cold-applied tapes have been known for a long time. No case
of external corrosion of pipelines immersed
in seawater has been detected so far using in-line inspection (ILI), despite,
most likely, the existence of some coating disbondment.
Despite the assumption of some coating disbondment in
seawater, corrosion protection is maintained, probably because the
high conductivity and homogeneity of seawater make it easier for the CP current
to access the exposed steel and protect it.
Summaries of our company's past
experience with various kinds of pipeline coatings have
been presented in previous papers.1-9 In particular, at the 16th International
Conference on Pipeline Protection in Paphos, the authors presented a
paper on failures recently discovered on "newer" coatings such as heat-shrinkable sleeves, threelayer
polyethylene (PE) coatings, and fusion-bonded epoxy (FBE) coatings.10 The present article first updates and completes
the information presented at the Paphos conference on the recent cases ofcoating failures encountered. It also summarizes the
results obtained from some laboratory test programs aimed at trying to explain
the problems for improving the future choices and the specifications of the
company.
Recent Feedback on Disbonding of Pipeline Coatings
Various practical case studies follow.
Cases related to heat-shrinkable sleeves (HSS) used for field joints and which
overlap the factory-applied 3- layer PE/polypropylene (PP) are the most
important as far as corrosion is concerned. Even if the problems related to
loss of adhesion of 3LPE/PP coatings do
not lead to significantcorrosion, the phenomenon must be better understood to prevent
the risk for the future.
Heat-shrinkable Sleeves Used for Field
Joint Coating
Recent in-line inspections (ILI) carried
out on a series of buried pipelines have shown massive disbonding of HSS with
significant corrosion underneath after 10 to 15 years of operation in
the ground. These coatingfailures and subsequent corrosion have been noticed principally at moderately
elevated temperatures (about 50-60 C [122-140 F]) and on coating systems that had been applied to a wire
brushcleaned surface specified at St 3 cleanliness level (~SSPC-SP 3, Power
Tool Cleaning), with or without application of a liquid epoxy primer before the
PE/PP. Specific examples of such failures are given below.
18-Inch Oil Pipeline in Gabon
In this case, presented earlier,10
external corrosion was detected through ILI on the first 15 km,
which is the hottest side (>55 C [131 F]) of the 18-inch Rabi-Batanga
oil pipeline, after 15 years of operation in the ground. The pipeline is buried in wet, compacted sand (pH of sample,
5.4). Heat-shrinkable sleeves were the hot-melt adhesive type and were applied
on a fast-curing liquid epoxy (of nominal maximum operating temperature 80 C
[176 F]). Wire brush cleaning as per St 3 was used for surface preparation. The
application was fully surveyed by a company inspector.
Massive disbonding of HSS on the steel
surface together with poor bonding of HSS on the 3LPE plant-appliedcoating at the overlaps had allowed water to penetrate
at the steel surface, leading to corrosion because
of the "CP shielding effect" (Fig. 1).
Further excavations of the pipeline revealed that the HSS residual adhesion to the
steel was also practically zero on sections at lower operation temperature
(down to 35 C [95 F]) but without significant corrosion.
16-Inch Oil Pipeline in Syria
ILI operations carried out on a 16-inch
x 7.1 mm wall thickness oil export pipeline operated
in Syria for about 12 years have revealed severe external corrosion at many girth weld areas. These areas had been
coated with HSS (hot-melt adhesive type) applied directly to a wire
brush-cleaned surface, without liquid epoxy primer (Fig. 2). Excavations have
confirmed the indications of ILI and revealed several corrosion craters underneath the surface of the field
joints with significant presence of mill scale. Corrosion is clearly due to disbondment of HSS. The
surface preparation was poor and the HSS overlap on the PE plant-applied coating was too small (1 cm).
The soil is very aggressive (brackish
water with a chloride concentration of 2 g/liter) and crystals of salt were
observed under the disbonded HSS. The soil is especially aggressive near the Al
Furat river, where the major defects were found. The area near the river is
very saline and has been intensively irrigated for a few years. In addition,
the temperature is high (> 55 C [131 F]) on the first 20 km of the pipeline, the most affected part. The corrosion appears to have been very high. The value of 0.7
mm/yr estimated as the maximum corrosionrate
under the disbonded coating at 50 C [122 F] in the laboratory study detailed
below roughly corresponds to the maximum corrosion rate
that could have been occurring here over 10 years of operation.
Other Cases
Similar cases were discovered recently,
again using ILI, on the 12-inch Coucal-Rabi pipeline,
again in Gabon, and on a 6-inch oil pipeline in
France (Paris basin). Again, the operating temperature was about 50 C [122 F]
in both cases.
Disbonding of 3LPE/PP Used in
Plant-Applied Coatings
Massive losses of adhesion of 3LPE coatings between the epoxy layer and the steel after 10
to 15 years' operations have been observed since 2004 through excavations
carried out after the detection of corrosion at
field joints under disbonded HSS. The disbondments of 3LPE have been noticed
most often when the operating temperature of the pipeline is about 50-60 C (122-140 F) in wet
environments. So far, no significant corrosionhas
been found underneath the disbondment of the 3LPE.
18-Inch Oil Pipeline in Gabon
Also presented earlier,10 disbonding of
a 3LPE coating occurred on the same 18-inch Rabi-Batanga pipeline in Gabon. The coating was a low-density PE. It was applied partly by
the side extrusion process (with PE adhesive applied by extrusion) and partly
by the longitudinal extrusion process (with PE adhesive applied by powder). The
application was in compliance with the company specification requiring a
minimum of 70 micrometers FBE beneath the PE.
The 3LPE plant-applied coating generally appeared to be correct externally but
was found fully disbonded between the FBE and steel when cut for inspection
with a tool at the excavation locations in the hottest part of the pipeline. Except for the presence of a layer of magnetite on
the steel surface, no significant corrosion of
the steel was noticed. Excavations showed that in a few cases, where some
minor corrosion was reported by ILI on a few pipe lengths, the
PE coating was found longitudinally cracked and open at the
3 o'clock and 9 o'clock positions. Measurements on PE samples taken at these
locations revealed a significant thermal aging effect (as shown by loss of
elongation at break, increase of viscosity, Shore D hardness and IR spectrum).
In addition to the details previously
given,10 it has been further noticed that loss of adhesion existed at
temperatures as low as 35 C (95 F), as shown in Fig. 3. In this case, as
compared with what was discovered at higher temperatures, the epoxy primer was
more visible and no magnetite had been formed. Also, it has been demonstrated
that this loss of bonding occurred with the two supplies of coated pipes, with
two differentcoating processes and with two different epoxy powders.
Peel strength and cathodic disbondment measurements carried out on spare pipes
that had been stored directly exposed to UV and atmospheric equatorial
conditions gave the results summarized in Table 1, which demonstrates again
that the loss of adhesion in the ground is related to exposure to soil
conditions (especially water diffusion). It is also notable that peel strength
is much higher with lateral extrusion as compared with longitudinal extrusion
(the difference is related to the type of adhesive) but that cathodic
disbondment is of the same order of magnitude (no significant difference
between the two epoxy powders), with the value measured at 60 C (140 F) being
very high.
Other Cases
Local disbondment has been observed on
the 16-inch Syrian oil pipeline on which severe corrosion was found under HSS (Fig. 4). In France, a short
length of pipeline with a 3LPP coating operating at
ambient temperature has suffered complete loss of adhesion without any corrosion. In this case, because all other inspected parts in
close vicinity did not show disbondment, this observation tends to demonstrate
that this loss of adhesion could be due to a specific application problem.
In Indonesia, a section of a 3LPP coated
offshore pipeline (with concrete weight coating) operating at about 80 C (176 F) has been cut out for
inspection related to internal corrosion.
Disbondment of 3LPP from the steel was observed, showing that disbondment seems
to be possible offshore also.
Laboratory Studies and an Engineering
Approach A Parametric Study of the "CP Shielding Effect" under
Disbonded Coatings
Gaz de France (Direction de la Recherche)
and Total have carried out studies in the Gaz de France laboratories to assess
the influence of the main parameters governing the corrosion rate underneath a simulated coatingdisbondment. In particular, the study assesses corrosion as a function of the distance from the point
where a direct contact exists with the external electrolyte. Parameters studied
were the height of the gap between the steel and the simulated disbonded coating, whether the water was stagnant or changed, the
resistivity of water, the application of various levels of cathodic protection,
and the absence of cathodic protection. All tests were carried out at ambient
temperature. The main results are discussed below. More details may be obtained
in published papers.11,12,13
The test plan is summarized in Table 2.
The detrimental effect of renewal of water was clearly demonstrated. In the
case of stagnant water, the corrosion rate
becomes practically zero, with or without cathodic protection within a few
centimeters of the artificial coating defect. Of
course, this testing does not take into account any possible development of
microbiologically induced corrosion (MIC) that could occur in the actual situation.
This result is easily explained by consumption of dissolved oxygen through the corrosion process. Any renewal of water increases
the corrosion rate when the distance from the artificial
defect increases, even when cathodic protection is applied. Some positive
effect can be seen when CP level is enhanced. The detrimental effect of increasing
the height of the gap between the steel and coating in the studied
range explains why disbondments seem to have generally no detrimental
consequence on corrosion with three-layer polyolefin (3LPO) systems: the
gap in the 3LPO systems remains very low, compared to the case of other coatings such as coal tar or asphalt enamels, tapes or
heat-shrinkable sleeves (HSS).
Analysis of the results shows a Gaussian
shape distribution of around 0.15 mm/yr with the maximum corrosionrate reaching 0.35 mm/yr. This distribution of corrosion rates may be interpreted as the same as seen on
a buried pipeline, at ambient temperature, that may be subjected
to coating disbonding without knowing the specific
combination of influencing parameters. This distribution also corresponds to
values commonly found in practice. For instance, NACE RP0502-200214 states that
a corrosion rate of 0.4 mm/yr under disbondedcoating may occur in the absence of any specific data.
Taking into account a general rule that the corrosionrate
is roughly multiplied by 2 when the temperature is increased above 30 C (86 F),
we may assume that the average corrosion rate
could be about 0.3 mm/yr and the maximum about 0.7 mm/yr at 50 C (122 F).
Field Joint Coatings
It is believed that disbonding of HSS
may be due to surface preparation by brush cleaning and the effect of higher
temperature. Corrosion under disbonded HSS may be due to
- the penetration of water through disbonded overlaps on plant-coating;
- the shielding effect preventing CP, together with a too weak "true" level of CP; or
- an increase in the corrosion rate because of the temperature.
For the time being, it has been decided
(at our company) to require, as a minimum before HSS application, Sa 2 1.2
abrasive blast cleaning of girth welds and a liquid epoxy primer applied for
onshore buried pipelines or when the temperature is higher than 50 C (122
F). However, the general trend is to apply, instead of HSS, liquid polyurethane
(PUR) or epoxy-modified polyurethane as a field joint coating onshore, which is currently being done on a
major gas pipeline in construction in Yemen (Fig. 5). The system
used a PUR-type product designed for 80 C (176 F) maximum operating
temperature. The application parameters, equipment, and personnel had been
accepted after a full qualification process comprising a Procedure
Qualification Trial (PQT) at the coating application
contractor premises and verification in the field at the start-up through a
Pre-Production Trial (PPT).
Tests carried out on samples taken from
the qualification trials were carried out by a third party laboratory, mainly
based on measurement of adhesion by pull-off test as per ISO 4624 and crosscut
tests before and after immersion in tap water at various temperatures (up to 80
C [176 F]) and after various durations (up to 28 days). Figure 6 illustrates
such a series of pull-off tests. As shown in Table 3, values obtained on the PE
plantcoating as well as directly on the steel surface were
found to be fully acceptable when the parameters of application were optimized
(especially the substrate temperature). Surface preparation was abrasive blast
cleaning to Sa 2 1.2 on steel and abrasion without any complementary treatment
on the PE.
In addition, Total is launching a
comparative program for an in-depth study of various field joint coatings(PE/PPbased HSS, liquid PUR or epoxy, flame sprayed
PE/PP, etc.), especially through hot water resistance testing and evaluation of
the compatibility of the HSS with plant coatings in
wet environments. For the HSS, two surface preparation levels will be tested:
Sa 2 1.2 (blasting to near white metal, SSPC-SP 10) and St 3 (very thorough
power tool cleaning, SSPC-SP 3 level of cleaning). For liquid products, various
surface treatments for the plantapplied coating will be tested:
with and without oxidative flame and/or other proprietary treatments. Tests
will consist of: cathodic disbonding (28 days at 23 C and 80 C [73 F and 176
F], and 48 hrs at 65 C [149 F]); peel tests on steel and plant coating at 23, 60, and 80 C and 100 C (for PP only);
impact tests per ASTM G14; immersion tests for 28 days in deionized water at 40
(104 F), 60, and 80 C; and, after immersion, peeling tests on steel and
overlap. Total will be happy to share this program with any interested party.
Efforts to Explain Disbondment Problems
of 3LPE/PP Coatings
Possible explanations for disbonding of
3LPE are
- water and oxygen diffusion through PE;
- water saturation and diffusion in FBE layer, depending on the type of epoxy;
- superficial corrosion of steel surface forming magnetite;
- all these steps being accelerated by temperature; and
- the possible effect of internal stresses in PE/PP due to the thermal history during application, which could help explain why such massive disbondment does not occur with FBE coatings. (FBE is not subject to thermal aging during application.)
Significant corrosion under disbonded 3LPE only occurs when it is also
cracked due to thermal ageing, which leads to a significant gap between the
disbonded coating and steel. The gap allows renewal of aggressive
species and the CP current shielding effect.
Since 2006, the efforts contributing to
the explanation of this phenomenon have concentrated on the following.
- Launching of a fundamental study as Ph.D. work on adhesion mechanisms of epoxy, as illustrated in another paper presented at the 17th International Conference on Pipeline Protection15
- Participation in a study on the development of a new accelerated test ensuring a better qualification that could predict long term behavior (carried out for EPRG, European Pipeline Research Group). Conventional peeling tests and cathodic disbonding tests used up to now failed for such a prediction. This study is still running and the results are confidential for the time being
- A study of water sensitivity of six epoxy powders, carried out by IFP (French Institute of Petroleum). The results of these tests are summarized in a paper also presented at the 17th International Conference onPipeline Protection.16
Hydrothermal Aging of LDPE
Thermal aging of various PE materials
(low density stabilized by ethylene vinyl acetate (EVA) or not, 2 types of
medium density) from various suppliers has been studied in wet conditions,
whereas the present methods used for qualification are restricted to dry
conditions. The question was: Does physicochemical thermal aging happen to PE
up to 100 C (212 F) in water?
The tests were carried out by
Korrosionstechnik Heim. The following test conditions were used: dry air at 100
C (212 F); demineralized water at 60 (140 F), 80 (176 F), and 100 C; and air
saturated with water vapor at 60 and 80 C. The effect of aging was assessed
using elongation and tensile strength at break and Melt Mass Flow Rate (MFR).
No significant change was noticed after 5,000 hours of testing for all products
and all test conditions. Consequently, no explanation has been given so far for
what was noted on the Rabi pipelinewhere cracking of PE topcoat in some locations led
to corrosion. Loss of the EVA additives is still the proposed
answer, but not a proven explanation. A bad batch of PE could be involved in
this issue.
Conclusion: Present Situation and Future
Work
The major corrosion problems are related to disbondment of
heat-shrinkable sleeves applied on field joints of buried pipelines. For Total, abrasive blast cleaning is now mandatory
before application of HSS and not only "recommended" for new
onshore pipelines. In addition, the general trend is to apply, instead
of HSS, liquid polyurethane (PUR) or epoxy for field joint coating onshore.
It is of utmost importance to
demonstrate whether an improvement of the adhesion safety margin of 3LPOcoatings is possible or not. If not, modification of
Total's basic choice could be changed in favor of FBE, in spite of the better
mechanical resistance of 3LPO coatings (generally
considered as a plus by pipe laying contractors). Parameters related to the
composition of epoxy powders have been studied. Methods such as measurement of
"Wet Tg" and the use of two-layer FBE/adhesive coatings are very promising approaches from lab studies.
However, the differences noted in water intake do not correlate with the severe
loss of adhesion of the coating when immersed in water, especially when water
temperature is above ambient. For the time being, the following criteria have
been introduced in Total's general specifications for selection of epoxy
primer: water absorption lower than 10% after 28 days at 80 C and "Wet
Tg" greater than maximum operating temperature +10 C above the operating
temperature.
The future work necessary for a better
knowledge of the problem of 3LPO disbondment will be researched through a
continuation of the studies at IFP, especially on test samples taken from
actual pipes recently coated for various projects, and also on other epoxy
powders and surface preparation systems. The Ph.D. work launched to better
understand the mechanism of bonding of epoxy to steel will address factors such
as mechanical vs. chemical anchor, surface preparation and treatment, and
internal stresses within the coating. In addition, the
study carried out in the U.S. on the internal stresses will be highly
profitable for the development of knowledge.17
Continuation of field experience
feedback will be organized in order to better know the influence of parameters
such as temperature or soil humidity. All possible efforts will be made to push
operating subsidiaries to perform excavations and field measurements in order
to contribute to and assess correlations between disbondment and soil and
operating parameters.
A more relevant accelerated aging test
allowing a better prediction of long term behavior remains to be established
(especially through EPRG collaboration) and implemented in the future revision
of ISO 21809 standards currently on the way of completion based on a
conventional approach.
Sumber : Melot, D; Paugam, G; Roche, M. "Disbondments of Pipeline Coatings and Their Effects on Corrosion Risks". 27 Januari 2014. http://search.proquest.com/docview/236015349?accountid=31562
Tidak ada komentar:
Posting Komentar