International pipeline contractors are playing key roles In constructing
some of the most sophisticated pipelines in the world. In recent months, they have
completed the world's most difficult pipeline construction
ever undertaken in terms of water depth and environment and set a record
for installing the longest subsea pipeline in
Australia.
Words like innovative technology and
state-of-the-art capabilities often come up when discussions turn to Saipem.
Although the company's expertise extends into land and offshore drilling, construction of offshoreproduction systems, petrochemical plants and the
laying of cross countrypipelines, a significant amount of engineering expertise is
spent to solve pipelay problems in the deepwater offshore environment.
For example, the company recently
completed the installation of two 24-inch diameter pipelines from Dzhubga on the Russian coast to Samsun,
Turkey. The Black Sea crossing was by far the most challenging aspect of the
entire 777-mile on and offshore Blue Stream Pipeline project.
Along the 236-mile subsea route, the two pipelines descend
to a record depth of nearly 7,060 feet.
Construction of Blue Stream project,
which carries a price tag in the $3 billion range, was started in spring 2001,
by the Turkish company BOTAS and Russia's Stroitransgas. Construction of the
319-mile Turkish onshore section and the 222-mile Russian portion, which
includes compressor stations and underground storage facilities, was completed
in September 2002.
Like everything else associated with the
Blue Stream project, mobilization of Saipem's semi-submersible heavy-lift
pipelay vessel, Saipem 7000, that installed the deepwater portion of the pipeline, required special planning. In preparation for the
Black Sea crossing, two massive cranes on the ship's deck had to be lowered and
the vessel's pipe lay tower dismantled and reinstalled. Also, before the
massive vessel could traverse under Istanbul's two suspension bridges and up
the Bosporus Strait to the Black Sea, it had to take on ballast until it
reached 95 feet of draft in order to pass under the first of the two bridges.
In February 2002, the Saipem 7000
completed laying the first of the two subsea lines, with work on the second
completed in June. Considered the most difficult pipeline construction project ever undertaken, along the
236-mile subsea route, the pipelines descend to a record depth of nearly 7,060 feet
and had to be installed in steep and irregular seabed areas off the coast of
both Russia and Turkey. Once installed, the twin pipelineswould be exposed to highly corrosive hydrogen sulfide.
Finding the right pipe for the harsh environment required several years of
research and numerous materials trials. The ultra deepwater and highly
corrosive marine environment resulted in the selection of a highly resistant
steel alloy API X65 flexible pipe with a triple layer of 4mm-thick
polypropylene factory applied coating to withstanding high temperature and
offering chemical resistance properties.
Several other products were developed to
provide pipeline protection in the unique environment, including
the world's first cross linked polypropylene, heat shrinkable sleeve to provide
joint protection for the compressor station on the Russian side, and at onshore
points where the on and offshore
pipelines are joined.
J-Lay Installation
The benefit of many years of experience
on every continent laying pipe in deep waters, put Saipem in the unique
position of being the only international operator currently capable of tackling
the installation of subseapipelines in
more than 7,000 feet of water.
The J-lay pipelay
technique used to install the dual subsea lines is specifically designed to
minimize stress on the pipe. Once launched from the Saipem 7000, the pipe sinks
under its own weight. Once on the seabed it must withstand significant
currents, and in the case of subsea earthquakes, offer enough elasticity to
absorb any resulting shocks.
The Russian seabed region posed some
specific challenges. Not only is it an area of active seismic activity, the
seabed is full of canyons, forcing the pipeline to
follow an oblique route. To ensure precise installation of
the pipeline on the seabed, the Saipem 7000 relied on its
dynamic positioning system to maintain the vessel's position and allow
pipelaying in up to Force 6 seas.
Russia is scheduled to deliver 70.6 Bcf
of natural gas to Turkey via the pipeline this
year. From 2003 to 2009, Russia will increase deliveries each year, with
the pipeline reaching peak capacity of 565 Bcf/year in 2009.
Duke Energy International (DEI) recently
inaugurated the Tasmanian Gas Pipeline,
which includes Australia's longest subsea pipeline project.
The new pipeline was specifically constructed to bring natural
gas to the island state of Tasmania and connects it to Australia's growing
natural gas network.
The US$246 million (A$440 million)
project includes 443 miles of subsea and underground pipeline and the conversion of the Bell Bay Power Station
on Tasmania to natural gas. The project will provide a much-needed energy
alternative for Australia's last state to receive natural gas.
DEI President and CEO Richard McGee said
the project completion marked an important international milestone for DEI.
"The Tasmanian Gas Pipeline delivers on a promise DEI made just a few short
years ago to bring a new, competitive and reliable energy supply to Tasmania to
fuel industrial growth and spur long-term employment opportunities in the
state," McGee said. "In four years, DEI has taken the project from
pipe dream to construction reality. We've invested in expanding Australia's
energy market, creating a new market in Tasmania and enhancing trading
opportunities nationally.
The new pipeline is made up of on and offshore segments. It starts at Longford in Victoria and
travels 13.6 miles to the Victorian coastline at Seaspray. From there, it
stretches 187.6 miles across Bass Strait, coming ashore at Five Mile Bluff,
northeast of George Town.
The onshore route, 235.5 miles, travels
from Bell Bay and splits at Westwood, a junction point just west of Launceston.
The northern pipeline extension is to Port Latta in northwest
Tasmania, and the southernpipeline extension is to Bridgewater, on the outskirts of
Hobart.
Bass Strait Construction
Allseas Group S.A., the Swiss-based
company that installed the pipeline in Bass Strait, is one of the world's
leading offshore pipelay and subsea construction companies. To
carry out the installation, the company mobilized its pipelay vessel Lorelay
from the U.S. Gulf of Mexico.
DEI Project Manager Carl Fisher said the
pipelaying process used in Bass Strait involved a number of steps. First,
coated pipe was loaded onto vessels that transported it out to the Lorelay.
Each steel pipe joint measured 39.3 feet in length and was coated with up to 80
mm of concrete. Once the pipe was aboard the Lorelay, crews relied on four
Phoenix semi-automatic welding machines to weld the pipe joints together before
ultrasonic testing and coating was carried out.
"As the Lorelay moved
forward," he said, "the pipe string was laid on the seabed." The
vessel is capable of laying around 2.5 miles of pipe a day, and operating 24
hours a day, depending on the weather and other factors."
In late August, Fisher said the Bass
Strait portion was complete and connected at each end to the onshore pipe.
Extensive testing of the line was also carried out to ready it for natural gas.
Onshore Construction
In discussing construction of the
onshore portion of the pipeline, Fisher noted that a number of contractors were
responsible for building this segment which extends from Bell Bay to Port Latta
in the northwest and from Bell Bay to Hobart in the south of the state.
A contract to construct the 149-mile
Five Mile Bluff to Port Latta (Stages 1 and 2) portion in Tasmania was won by
McConnell Dowell Constructors (Australia) Pty Ltd.
Construction of the 102-mile Westwood to
Bridgewater (Stage 3) portion in Tasmania was awarded to Nacap Australia Pty
Ltd.
Fisher said that the onshore portion of
the project was buried at varying depths, depending on land use and other
factors such as proximity to existing building and cities. For river and
roadway crossings on the project, contractors relied on several methods.
Horizontal directional drills (HDD) were used to make major roadway and large
and sensitive water crossings, while boring and open cut were used for more
traditional crossings.
A team of eight DEI environmental
specialists was charged with rehab and revegetation on the project, which
involved collecting thousands of seeds in bush areas and establishing more than
20,000 plants and shrubs which were grown in several Tasmanian nurseries.
Record Setting
River Crossing
In addition to completing drills at Five
Mile Bluff and under rivers in northern Tasmania, an Australian record was
achieved when McConnell Dowell and its subcontractor, Stockton AJ Lucas Joint
Venture, a drilling company owned by McConnell Dowell and AJ Lucas,
successfully completed the country's longest HDD beneath the Tamar River.
The 6,712-foot curved crossing
"punched" through at Rowella on the west bank of the Tamar River on
March 22 precisely at the designated exit point. The curved drill reached 282
feet beneath the bed of the river.
Fisher said the successful Tamar River
crossing was a significant achievement and set an HDD length record in
Australia. An additional 11 rivers in northern Tasmania were crossed using HDD.
In all, Stockton-Lucas completed 12 major river crossing in just seven weeks
using four drilling rigs.
At the peak of construction, 1,018
people were working on and offshore to complete the project.
Safety
Now completed, the pipeline is being controlled and monitored 24 hours a day
via a SCADA system. System features include an automatic alarm system to
alert pipeline controllers to any abnormal operating conditions
on the line
Sumber : Tubb, Rita. "Blue Stream: The world's Most Difficult Pipeline Installation". 29 Januari 2014. http://search.proquest.com/docview/197495562?accountid=31562


Tidak ada komentar:
Posting Komentar